GAO Issues More Cost Warnings For F-35 (aviationweek.com)
2 points by protomyth on March 25, 2014 | hide | past | favorite | 1 comment



"The program’s continued failure to develop and test mission software on schedule will also either result in delayed initial operational capability (IOC) dates, or in further reductions to the capability delivered at IOC, the report predicts."

and

"By January, the GAO says, the program had verified only half as much of the Block 2B software – the Marine Corps IOC standard – as planned, 13% versus 27%. The GAO endorses the DOT&E’s estimate of a delay as long as 13 months, and recommends a new assessment by the Office of the Secretary of Defense “of the specific capabilities that can be delivered and those that will not likely be delivered” to the services at their different IOC dates."